price of concrete per m3
anyone know a rough current price for concrete per m3 ?

71 notchback,
Past owner of, 70 NB, 73 SB and 72 FB TLE
|
|
Kuchster
A.k.a.: Robert Kuch
Insano Dub Head
  
Posts: 762
Threads: 182
Registered: September 6th, 2003
Member Is Offline
Location: Sydney
Theme: UltimaBB Pro Blue ( Default )
|
posted on April 23rd, 2011 at 06:49 PM |
|
|
Starts at around $160 for a concreter, you wont find much cheaper, unless they buy a lot more but im not sure how much more it would drop by. Some pay
$180 or $190
|
|
11CAB
Compulsive Aussie Vee Dubber
If ya got it....Baja it
     
Posts: 4674
Threads: 321
Registered: August 30th, 2002
Member Is Offline
Location: Brisbane Northside
Theme: UltimaBB Pro Blue
Mood: Beach'n
|
posted on April 23rd, 2011 at 08:58 PM |
|
|
I just got a 6x6 slab put in for about $2600 for my shed
65 Meyers Manx
68 Country Buggy (KO 367)
68 Country Buggy (KO 669)
68 Country Buggy (KO 789)
68 Country Buggy (KO 815)
68 Baja Bug
76 Baja Kombi Twincab
|
|
ahoogah
Seriously Crusin Dubber

Posts: 135
Threads: 20
Registered: October 4th, 2009
Member Is Offline
Location: Gold Coast
Theme: UltimaBB Pro Blue ( Default )
|
posted on April 23rd, 2011 at 09:34 PM |
|
|
Depends on the strength you need,mix design, the distance from the batch plant and volume.
Minimum cartage rate of 3m.
Mini mix dearer.
Ring around for best price,everyone is keen atm.
|
|
whathaveidone
Custom Title Time!
   
Posts: 1559
Threads: 98
Registered: February 24th, 2010
Member Is Offline
Location: Dapto
Theme: UltimaBB Pro Blue ( Default )
Mood: Heading for 10.99
|
posted on April 23rd, 2011 at 09:47 PM |
|
|
Quote: | Originally
posted by 11CAB
I just got a 6x6 slab put in for about $2600 for my shed
|
Hope that was 6mX6m??????Otherwise if ill do your next one if you want
|
|
11CAB
Compulsive Aussie Vee Dubber
If ya got it....Baja it
     
Posts: 4674
Threads: 321
Registered: August 30th, 2002
Member Is Offline
Location: Brisbane Northside
Theme: UltimaBB Pro Blue
Mood: Beach'n
|
posted on April 23rd, 2011 at 10:03 PM |
|
|
Yeah 6m x 6m
65 Meyers Manx
68 Country Buggy (KO 367)
68 Country Buggy (KO 669)
68 Country Buggy (KO 789)
68 Country Buggy (KO 815)
68 Baja Bug
76 Baja Kombi Twincab
|
|
vlad01
Compulsive Aussie Vee Dubber
     
Posts: 4270
Threads: 109
Registered: June 3rd, 2010
Member Is Offline
Location: Kyneton, VIC
Theme: UltimaBB Pro Blue ( Default )
Mood: Side ways
|
posted on April 23rd, 2011 at 10:45 PM |
|
|
ok so lets say average $175 per m3.
ok 18 x 10 ummm 5 inch? I wont be driving any heavy vehicles.
so where was I? oh yeah 18 x 10 x 0.127 = 22.86m3 = $4k just for concrete
x 2 the price for reo, plastic and labor only the concreting itself. My team and I will be doing the digging, leveling, compacting, plastic, foam
separators etc...
yeah 8k is doable. My half bro does sheds and has been doing for well over 20 year, he actually built my shed. Got some friends of his who do
concreting for a living which will join the project
at a mates rate dam I feel cheap. My half bros idea I swear!

71 notchback,
Past owner of, 70 NB, 73 SB and 72 FB TLE
|
|
ahoogah
Seriously Crusin Dubber

Posts: 135
Threads: 20
Registered: October 4th, 2009
Member Is Offline
Location: Gold Coast
Theme: UltimaBB Pro Blue ( Default )
|
posted on April 24th, 2011 at 07:20 AM |
|
|
Always a good idea to get the subgrade checked by the floorlayer before reo goes down,nothing worse than lack of cover.
Plenty of excellent floorlayers about will work for collin ash.
At 180m/2 you will need a few men,may need to factor in a concrete pump depending how solid the ground is.
|
|
mactaylor
Custom Title Time!
   
Posts: 1005
Threads: 54
Registered: August 14th, 2007
Member Is Offline
Location: Albury
Theme: UltimaBB Pro Blue
Mood: even my dog is german
|
posted on April 24th, 2011 at 07:42 AM |
|
|
going rate around albury for crete about $180m3 place and finnish $22-$35 per m2 no earth works. its a good time of the year to get helpers in as
theres not much on, concrete pump costs bout $130 an hour minimum 3 hrs $5m3 wear charge and $3 a klm.
EVERLAST CONCRETE TANKS
1800 552 123
|
|
vlad01
Compulsive Aussie Vee Dubber
     
Posts: 4270
Threads: 109
Registered: June 3rd, 2010
Member Is Offline
Location: Kyneton, VIC
Theme: UltimaBB Pro Blue ( Default )
Mood: Side ways
|
posted on April 24th, 2011 at 09:42 AM |
|
|
Quote: | Originally
posted by ahoogah
Always a good idea to get the subgrade checked by the floorlayer before reo goes down,nothing worse than lack of cover.
Plenty of excellent floorlayers about will work for collin ash.
At 180m/2 you will need a few men,may need to factor in a concrete pump depending how solid the ground is.
|
yeah we got all that factored in. I got a budget of 9-9.5K for the project. The concreting mates we have, have got all the equipment and helicopter.

71 notchback,
Past owner of, 70 NB, 73 SB and 72 FB TLE
|
|
Adsman
Officially Full-On Dubber
 
Posts: 393
Threads: 21
Registered: January 23rd, 2007
Member Is Offline
Location: Townsville
Theme: UltimaBB Pro Blue ( Default )
|
posted on April 24th, 2011 at 03:26 PM |
|
|
hmmm great to be in the know
Got mine done nearly three years ago but keeping in mind i lived in north qld and everything is more expensive
12 x 18 bonded beam slab reinforced in roller door bays with 2m cubic hoist reinforcing beam = 30odd metres of concrete, cost $185 a metre plus milage
surcharge, helicopter finished, 6 workers and bobcat hired $24k job in 8hours kinda makes you feel sick when you look at it that way
never the less love the concrete floor good jobs cost money
probably should add that it was increased hardness concrete and had slower cure additive put in to reduce cracking
What my garage isn't messy........Well chaos is a form of order isn't it?
|
|
vlad01
Compulsive Aussie Vee Dubber
     
Posts: 4270
Threads: 109
Registered: June 3rd, 2010
Member Is Offline
Location: Kyneton, VIC
Theme: UltimaBB Pro Blue ( Default )
Mood: Side ways
|
posted on April 24th, 2011 at 04:20 PM |
|
|
f**king hell! that expensive as hell 
We have man power with several people, which only 1 or 2 are being hired at a mates rate anyway. My half bro has a vibrating roller, excavator, normal
vibrator plate.
He also can get all the GST back for me as heel can put it under his business. So we estimated 8.5k with extra 500-1000 buks in case whatever and
this was estimated on a 20 x 15 slab
so when i measured it and got 18 x 10, realistically we got 7-8k but I have 9-9.5k anyway.
I wont be doing it in 8 hrs. the preparation will be a week or 2.

71 notchback,
Past owner of, 70 NB, 73 SB and 72 FB TLE
|
|
matberry
Super Moderator
Go hard or go home
     
Posts: 8114
Threads: 134
Registered: March 7th, 2006
Member Is Offline
Location: Cooroy Qld
Theme: UltimaBB Pro Blue
Mood: enjoying waving at all my Kombi buddies from my T3
|
posted on April 24th, 2011 at 05:42 PM |
|
|
Amazing how it pays to get quotes. 5 years ago now, building house and shed at the same time, shed is 12 x 18, house slab similar area, quotes varied
from 20k to over 40k. I got both and another for water tanks with uprated concrete for about 24 all done.
Matt Berry Motorsports...air cooled advice, repairs and mods Ph 0408 704 662
OFF-ROAD,CIRCUIT,DRAG,STREET,ENDURANCE

|
|
Adsman
Officially Full-On Dubber
 
Posts: 393
Threads: 21
Registered: January 23rd, 2007
Member Is Offline
Location: Townsville
Theme: UltimaBB Pro Blue ( Default )
|
posted on April 25th, 2011 at 01:04 PM |
|
|
lol you can add another 10-14k on that price for other quotes. Gee I love north QLD.....
What my garage isn't messy........Well chaos is a form of order isn't it?
|
|
mactaylor
Custom Title Time!
   
Posts: 1005
Threads: 54
Registered: August 14th, 2007
Member Is Offline
Location: Albury
Theme: UltimaBB Pro Blue
Mood: even my dog is german
|
posted on April 25th, 2011 at 05:59 PM |
|
|
yeah quotes are varied but the top end dudes all seem to hang around the same usually bout $65 m2 all up but this can vary as the site and soil
changes and who the quote is for, double it if its for a teacher or triple for a university lecturer!
EVERLAST CONCRETE TANKS
1800 552 123
|
|
volumex
Officially Full-On Dubber
 
Posts: 389
Threads: 35
Registered: July 1st, 2005
Member Is Offline
Location: Sarnia, ON
Theme: UltimaBB Pro Blue ( Default )
|
posted on April 25th, 2011 at 07:16 PM |
|
|
Quote: | Originally
posted by vlad01
ok 18 x 10 ummm 5 inch? I wont be driving any heavy vehicles.
|
I'll talk to some of the civil engineers at work and see how thick it needs to be.
Is it just for working on cars? Any plans for hoists or jib cranes etc?
|
|
ahoogah
Seriously Crusin Dubber

Posts: 135
Threads: 20
Registered: October 4th, 2009
Member Is Offline
Location: Gold Coast
Theme: UltimaBB Pro Blue ( Default )
|
posted on April 25th, 2011 at 07:37 PM |
|
|
Quote: | Originally
posted by volumex
Quote: | Originally
posted by vlad01
ok 18 x 10 ummm 5 inch? I wont be driving any heavy vehicles.
|
I'll talk to some of the civil engineers at work and see how thick it needs to be.
Is it just for working on cars? Any plans for hoists or jib cranes etc?
|
The nine words that construction coalface personnel do not want to hear?
"I am an engineer,I am here to help"
|
|
vlad01
Compulsive Aussie Vee Dubber
     
Posts: 4270
Threads: 109
Registered: June 3rd, 2010
Member Is Offline
Location: Kyneton, VIC
Theme: UltimaBB Pro Blue ( Default )
Mood: Side ways
|
posted on April 25th, 2011 at 09:05 PM |
|
|
I have been recommended I should only need 3-4".
yeah right, so i talked to my half bro who was and engineer for over 30 years and did sheds on the side and still does.
He recommended 5" he has 6" in his 2 sheds which has a massive fork and 10 ton truck and few 10 ton lathes and he even used to have a 35 ton
lathe.
No problems at all. its all in the base preparation. hell I could go 6" for extra 500 buks.
I may have a hoist one day? possibly a small fork? for what I don't know. Yeah the shed will only be for cars. I do plan for a gantry system but
that's nothing to do with the slab.

71 notchback,
Past owner of, 70 NB, 73 SB and 72 FB TLE
|
|
BiX
Veteran Volks Folk
   
Posts: 2499
Threads: 154
Registered: September 2nd, 2002
Member Is Offline
Location: Brisbane
Theme: UltimaBB Pro Blue ( Default )
|
posted on April 26th, 2011 at 11:56 AM |
|
|
Your brother is right, subgrade is the key. Its almost like body work, the prep really makes the finished product. 100mm is not out of the question
for a light weight slab.
I have no sympathy for my car, only the wallet that pays for it!
Go hard or go home!!!!
|
|
beetleboyjeff
A.k.a.: Jeff Walsh
Custom Title Time!
   
Posts: 1779
Threads: 40
Registered: February 13th, 2009
Member Is Offline
Location: Port Macquarie
Theme: UltimaBB Pro Blue ( Default )
Mood: Drive bugs hard
|
posted on April 26th, 2011 at 12:10 PM |
|
|
Quote: | Originally
posted by BiX
100mm is not out of the question for a light weight slab.
|
As a builder, I would agree with this, and the preparation statement. You could even just thicken the slab where you may want a hoist later, or
strengthen the slab with beams in it. You may well need beams around the edges, depending on what type of construction your shed will be.
Interestingly on the concrete price, we were paying almost $200 m3 for 25mgp concrete in Port Macquarie over 12 months ago, and I just got a quote in
Parkes, and it was just over $ 200 m3 for 20mgp concrete. Maybe just check with your local supplier for their current price - should only need a phone
call.
From your ole' mate Jeff
|
|
waltermitty
Custom Title Time!
Legend when my beer goggles are on
   
Posts: 1993
Threads: 268
Registered: August 29th, 2002
Member Is Offline
Location: Port Macquarie now Yipee!
Theme: UltimaBB Pro Grey
Mood: Hungry for mor
|
posted on April 26th, 2011 at 12:27 PM |
|
|
Quote: | Originally
posted by vlad01
ok so lets say average $175 per m3.
ok 18 x 10 ummm 5 inch? I wont be driving any heavy vehicles.
so where was I? oh yeah 18 x 10 x 0.127 = 22.86m3 = $4k just for concrete
x 2 the price for reo, plastic and labor only the concreting itself. My team and I will be doing the digging, leveling, compacting, plastic, foam
separators etc...
yeah 8k is doable. My half bro does sheds and has been doing for well over 20 year, he actually built my shed. Got some friends of his who do
concreting for a living which will join the project
at a mates rate dam I feel cheap. My half bros idea I swear!
|
Your budget is missing BEER all concreters drink their weight in beer immediately the job is screed. I believe the rate increases for mate rates. M
23 windows ...8 too many!
|
|
HappyDaze
A.k.a.: Greg Mackie
Son of Jim - Creator of Good
Superannuated
    
Posts: 2887
Threads: 141
Registered: June 13th, 2009
Member Is Offline
Location: Southern Highlands NSW
Theme: UltimaBB Pro Blue ( Default )
Mood: Happy enough
|
posted on April 26th, 2011 at 12:32 PM |
|
|
It surprises me that no-one has mentioned the importance of STEEL in all of this. Without reo., concrete is not much good - no matter how thick!
I'd rather wear a Beetle out by racing it than by polishing it!
|
|
silver
Veteran Volks Folk
Dangerous when poked
   
Posts: 2169
Threads: 162
Registered: December 8th, 2002
Member Is Offline
Location: Sydney
Theme: UltimaBB Pro Blue ( Default )
Mood: In 2 Minds
|
posted on April 26th, 2011 at 12:38 PM |
|
|
and an edge beam with steel as well
Keeping it real !
|
|
norbert
Officially Full-On Dubber
Comedian in training
 
Posts: 317
Threads: 54
Registered: January 8th, 2009
Member Is Offline
Location: Canberra - help outsource our pollies
Theme: UltimaBB Pro Blue
Mood: intellectually challenged and chilling
|
posted on April 26th, 2011 at 12:41 PM |
|
|
9-10 grand even with mates rates is cheap. I paid 26 grand 26 years ago doing my house slab which is 210 m2. Granted its near Canberra and Pub rates
apply even if your not one of them.
Jetzt mache ich meinen Karmann und Käfer zusammen.
|
|
ahoogah
Seriously Crusin Dubber

Posts: 135
Threads: 20
Registered: October 4th, 2009
Member Is Offline
Location: Gold Coast
Theme: UltimaBB Pro Blue ( Default )
|
posted on April 26th, 2011 at 12:53 PM |
|
|
Quote: | Originally
posted by HappyDaze
It surprises me that no-one has mentioned the importance of STEEL in all of this. Without reo., concrete is not much good - no matter how thick!
|
Reo doesn't give any more strength on ground slabs,just holds the concrete together if it cracks.
Adequately solid subgrade is more important.
|
|
vlad01
Compulsive Aussie Vee Dubber
     
Posts: 4270
Threads: 109
Registered: June 3rd, 2010
Member Is Offline
Location: Kyneton, VIC
Theme: UltimaBB Pro Blue ( Default )
Mood: Side ways
|
posted on April 26th, 2011 at 06:50 PM |
|
|
Quote: | Originally
posted by waltermitty
Quote: | Originally
posted by vlad01
ok so lets say average $175 per m3.
ok 18 x 10 ummm 5 inch? I wont be driving any heavy vehicles.
so where was I? oh yeah 18 x 10 x 0.127 = 22.86m3 = $4k just for concrete
x 2 the price for reo, plastic and labor only the concreting itself. My team and I will be doing the digging, leveling, compacting, plastic, foam
separators etc...
yeah 8k is doable. My half bro does sheds and has been doing for well over 20 year, he actually built my shed. Got some friends of his who do
concreting for a living which will join the project
at a mates rate dam I feel cheap. My half bros idea I swear!
|
Your budget is missing BEER all concreters drink their weight in beer immediately the job is screed. I believe the rate increases for mate rates. M
|
is 200 buks in beer good? lol. I wouldn't know I don't drink.
Oh yeah talked to me half bro agian, he has 5" in the shed that used to have the 40 ton lathe and the fork. No probs. So 5" it is.

71 notchback,
Past owner of, 70 NB, 73 SB and 72 FB TLE
|
|
vlad01
Compulsive Aussie Vee Dubber
     
Posts: 4270
Threads: 109
Registered: June 3rd, 2010
Member Is Offline
Location: Kyneton, VIC
Theme: UltimaBB Pro Blue ( Default )
Mood: Side ways
|
posted on April 26th, 2011 at 06:55 PM |
|
|
Quote: | Originally
posted by norbert
9-10 grand even with mates rates is cheap. I paid 26 grand 26 years ago doing my house slab which is 210 m2. Granted its near Canberra and Pub rates
apply even if your not one of them.
|
I told my bro about the prices mentioned here in this thread.
he has never heard of such high prices before. must be the labor in preparation? i guess you don't pay yourself for the work you do yourself.

71 notchback,
Past owner of, 70 NB, 73 SB and 72 FB TLE
|
|
vlad01
Compulsive Aussie Vee Dubber
     
Posts: 4270
Threads: 109
Registered: June 3rd, 2010
Member Is Offline
Location: Kyneton, VIC
Theme: UltimaBB Pro Blue ( Default )
Mood: Side ways
|
posted on April 26th, 2011 at 07:02 PM |
|
|
Quote: | Originally
posted by ahoogah
Quote: | Originally
posted by HappyDaze
It surprises me that no-one has mentioned the importance of STEEL in all of this. Without reo., concrete is not much good - no matter how thick!
|
Reo doesn't give any more strength on ground slabs,just holds the concrete together if it cracks.
Adequately solid subgrade is more important.
|
yeah that is already factored in. will be around 2400 buks including delivery. That is the first thing i am buying.

71 notchback,
Past owner of, 70 NB, 73 SB and 72 FB TLE
|
|
mactaylor
Custom Title Time!
   
Posts: 1005
Threads: 54
Registered: August 14th, 2007
Member Is Offline
Location: Albury
Theme: UltimaBB Pro Blue
Mood: even my dog is german
|
posted on April 26th, 2011 at 09:31 PM |
|
|
as mentioned steel is only for crack control in a ground slab, however i did a slab afew years back that was 350mm thick top and bottom sl101 mesh for
a forge around here that supports 40 tonne manipulator that picks up red hot 15 tonne billets and on occasion drops them! so far so good!
EVERLAST CONCRETE TANKS
1800 552 123
|
|
donn
Wolfsburg Elder
     
Posts: 3515
Threads: 428
Registered: November 30th, 2005
Member Is Offline
Location: NEWCASTLE NSW
Theme: UltimaBB Pro Blue
Mood: LAID BACK AND CONFUSED
|
posted on April 27th, 2011 at 10:45 AM |
|
|
Of course reo is for crack controll, concreye is good in compression but rat shit in tension, if your ground moves then the top of the slab will be
either in compresion or tension and the bottom of the slab will be in the opposite situation, delete reo in slab on ground at your own risk. Hear
endeth the lesson.